The Regional Connectivity Program (RCP) is an Australian Commonwealth Government grants program funding the delivery of ‘place-based’ telecommunications infrastructure projects that aim to improve digital connectivity across regional, rural, and remote Australia. Field Solutions has been awarded funding under RCP1 to deliver 16 networks and one additional network under RCP2.

The FSG Engineering & Infrastructure team have been busy travelling the countryside undertaking “Site Caravans” in search of suitable locations to build our towers. Thanks to the support of so many regional councils and landowners, we have much acquisition underway.

The weather, however, has played its part, especially on the east coast of Australia over last 12 months. It doesn’t help with undertaking activities such as geotechnical analysis, nor does it aid in constructing towers. It’s not just the hole we dig for the foundations, filling with water; it’s ensuring the access tracks we need to use for construction (and adjacent paddocks) don’t become a quagmire – especially given that we share these with landowners who need them all year round. It’s a challenge, but finding solutions is what we’re all about. And the great news is the hard work and tenacity of the team is paying with off with construction kicked off on one network with many more to follow!

Bollon Network Starts Build!

As part of this project, FSG is deploying four sites between St George and Bollon, all of which will be delivering fixed wireless access, mobility and IoT services.  I know the folk at Bollon cannot wait for this deployment and big shout out to the team at Balonne Regional Council and landholders for their support to date.  Great communication and collaboration has resulted in this being a relatively quick and easy process for the teams.

 

 

 

 

 

All four towers are now stood and, in a few weeks, the FSG Field engineering team will move into the area and start works on solar solution, ground equipment installation and attach our antenna and radio equipment on the towers ahead of a go live shortly after that!

Our team is always here to answer your questions, so please feel free to reach out and drop an email to govprograms@fieldsolutions-group.com, and one of the team will get back to you.

Network by State

NSW

VIC

QLD

WA

NT

Bourke

Swan Hill

Balonne

Midlands

Blackall Tambo

Gunnedah

Isacc

Leeton

Moree

Napranum


Warren-Narromine

Paroo-Bulloo

More detailed project info

Network Names

Project ID

Project Asset ID

RFNSA ID

Asset Name

Status

Indicative
Rollout
Timeframe

Moree NSW

RCP-R1-201

RCP-R1-201-A

Collarenabri Water Tower

Working on a co-location with BAI.

Dec 24

Moree NSW

RCP-R1-201

RCP-R1-201-B

Collymongle

Site On Air.

Dec 24

Moree NSW

RCP-R1-201

RCP-R1-201-C

Bullarah

Site On Air.

Dec 24

Moree NSW

RCP-R1-201

RCP-R1-201-D

West Moree

Site build commenced. 

Dec 24

Moree NSW

RCP-R1-201

RCP-R1-201-E

Pallamallawa

Under commissioning.

Sep 24

Moree NSW

RCP-R1-201

RCP-R1-201-F

Gravesend Mountain

Site acquired. Build
plans now underway. Tower ready for transport to site.

Dec 24

Moree NSW

RCP-R1-201

RCP-R1-201-G

North Star

Site acquired. Build plans now underway. Tower ready for transport to site.

Dec 24

Moree NSW

RCP-R1-201

RCP-R1-201-H

Koramba Gin

All approvals are in place.

Dec 24

Warren Narromine NSW

RCP-R1-202

RCP-R1-202-A

Milawa

Under construction.

Dec 24

Warren Narromine NSW

RCP-R1-202

RCP-R1-202-B

Haddon Rig

Under construction.

Dec 24

Warren Narromine NSW

RCP-R1-202

RCP-R1-202-C

Burroway 

Under construction.

Dec 24

Warren Narromine NSW

RCP-R1-202

RCP-R1-202-D

Wyanga

Ready for construction.

Dec 24

Warren Narromine NSW

RCP-R1-202

RCP-R1-202-E

Narromine Water Tower

Under build.

Dec 24

Warren Narromine NSW

RCP-R1-202

RCP-R1-202-F

Old Narwonah

Under construction.

Dec 24

Warren Narromine NSW

RCP-R1-202

RCP-R1-202-G

Barton

Ready for construction.

Dec 24

Warren Narromine NSW

RCP-R1-202

RCP-R1-202-H

Narromine East

Under construction.

Dec 24

Bourke NSW

RCP-R1-203

RCP-R1-203-A

Bourke Water Tower

Under construction.

Dec 24

Bourke NSW

RCP-R1-203

RCP-R1-203-B

North Bourke

Ready for construction.

Dec 24

Bourke NSW

RCP-R1-203

RCP-R1-203-C

Bourke South East

Ready for construction.

Dec 24

Gunnedah NSW

RCP-R1-204

RCP-R1-204-A

Gunnedah Town

Smart pole ordered. Power supply being implemented.

Dec 24

Gunnedah NSW

RCP-R1-204

RCP-R1-204-B

Porcupine Hill

Build program scheduled.

Dec 24

Gunnedah NSW

RCP-R1-204

RCP-R1-204-C

Kelvin North

Build program scheduled. Tower being delivered to site.

Dec 24

Gunnedah NSW

RCP-R1-204

RCP-R1-204-D

Gunnedah North

Build program scheduled. Tower being delivered to site.

Dec 24

Gunnedah NSW

RCP-R1-204

RCP-R1-204-E

Governor Mountain

Site variation for cancellation awaiting determination by Commonwealth.

Dec 24

Gunnedah NSW

RCP-R1-204

RCP-R1-204-F

Somerton

Lease agreement in place. Rigging works scheduled.

Dec 24

Gunnedah NSW

RCP-R1-204

RCP-R1-204-G

Breeza

Ready for construction.

Dec 24

Gunnedah NSW

RCP-R1-204

RCP-R1-204-H

Pine Ridge

Build program scheduled. Tower being delivered to site.

Dec 24

Gunnedah NSW

RCP-R1-204

RCP-R1-204-L

Caroona

Site acquisition
underway with DA to
be submitted.

Dec 24

Gunnedah NSW

RCP-R1-204

RCP-R1-204-M

Spring Ridge

Build program scheduled. Tower being delivered to site.

Dec 24

Swan Hill NSW

RCP-R1-212

RCP-R1-212-A

Kooloonong

All approvals are in place.

Dec 24

Swan Hill NSW

RCP-R1-212

RCP-R1-212-B

Piangil

Site stood. Equipment
under deployment.

Dec 24

Swan Hill NSW

RCP-R1-212

RCP-R1-212-C

Nyah

Site stood. Equipment
under deployment.

Dec 24

Swan Hill NSW

RCP-R1-212

RCP-R1-212-D

Swan Hill 

Site stood. Equipment
under deployment.

Dec 24

Swan Hill NSW

RCP-R1-212

RCP-R1-212-E

Mallee Highway 

All approvals are in place.

Dec 24

Swan Hill NSW

RCP-R1-212

RCP-R1-212-F

Kyalite North

All approvals are in place.

Dec 24

Bollon QLD

RCP-R1-205

RCP-R1-205-A

Kurray

Site on Air.

Aug 24

Bollon QLD

RCP-R1-205

RCP-R1-205-B

Kurray - Bollon 1

Site on Air.

Aug 24

Bollon QLD

RCP-R1-205

RCP-R1-205-C

Kurray - Bollon 2

Site on Air.

Aug 24

Bollon QLD

RCP-R1-205

RCP-R1-205-D

Kurray - Bollon 3

Site on Air.

Aug 24

Bollon QLD

RCP-R1-205

RCP-R1-205-E

Bollon Township

Site on Air.

Aug 24

Blackall-Tambo QLD

RCP-R1-200

RCP-R1-200-A

Tambo Tower (Existing 35m)

Site design complete and deployment is being scheduled.

Dec 24

Blackall-Tambo QLD

RCP-R1-200

RCP-R1-200-B

Landsdowne

Tower ordered for the site. Build program development is underway.

Dec 24

Blackall-Tambo QLD

RCP-R1-200

RCP-R1-200-C

Bayrick

Tower ordered for the site. Build program development is underway.

Dec 24

Blackall-Tambo QLD

RCP-R1-200

RCP-R1-200-D

Highfields

Tower ordered for the site. Build program development is underway.

Dec 24

Blackall-Tambo QLD

RCP-R1-200

RCP-R1-200-E

Scrubby Creek

Tower ordered for the site. Build program development is underway.

Dec 24

Isacc QLD

RCP-R1-206

RCP-R1-206-A

Clermont Showgrounds

Site design with council for approval.

Dec 24

Isacc QLD

RCP-R1-206

RCP-R1-206-B

Logan Creek

All relevant documentation is being prepared for submission to Council.

Dec 24

Isacc QLD

RCP-R1-206

RCP-R1-206-C

Wentworth

All relevant documentation is being prepared for submission to Council.

Dec 24

Isacc QLD

RCP-R1-206

RCP-R1-206-D

Moranbah Water Tower

Council discussions are underway for approval to proceed.

Dec 24

Isacc QLD

RCP-R1-206

RCP-R1-206-F

Glenidol

All relevant documentation is being prepared for submission to Council.

Dec 24

Napranum QLD

RCP-R1-210

RCP-R1-210-A

Napranum

DA approved. Tower has been ordered and build plan is in progress.

Dec 24

Paroo-Bulloo QLD

RCP-R1-208

RCP-R1-208-A

Cunamulla East

All approvals are in place.

Dec 24

Paroo-Bulloo QLD

RCP-R1-208

RCP-R1-208-B

Cunamulla to Thargo - Paroo side

Tower is on site. Tower assembly works are underway. Remaining civil works are underway.

Dec 24

Paroo-Bulloo QLD

RCP-R1-208

RCP-R1-208-C

Cunamulla to Thargo - Bulloo side

Tower is on site. Tower assembly works are underway. Remaining civil works are underway.

Dec 24

Midlands WA

RCP-R1-217

RCP-R1-217-A

Moora EE POI

Deployment complete.

July 23

Midlands WA

RCP-R1-217

RCP-R1-217-B

Wongan EE POI

Deployment complete.

Oct 23

Midlands WA

RCP-R1-217

RCP-R1-217-A

Moora

Tower stood. LTE equipment to be fitted shortly. Power system to be expanded shortly..

Oct 24

Midlands WA

RCP-R1-217

RCP-R1-217-D

Watheroo

Site acquired. Build schedule being finalised.

Oct 24

Midlands WA

RCP-R1-217

RCP-R1-217-e

Balidu

Site acquired. Build to
be scheduled.

Dec 24

Midlands WA

RCP-R1-217

RCP-R1-217-F

Wongan Hills

Council tower identified
as suitable for
project. Acquisition
underway with council
including structural
assessment. Detailed
design underway.

Dec 24

Midlands WA

RCP-R1-217

RCP-R1-217-G

Dalwallinu

Site acquired. Build schedule being finalised. Tower ready for delivery.

Dec 24

Midlands WA

RCP-R1-217

RCP-R1-217-H

Coomberdale

Site acquired. Build schedule being finalised. Tower ready for delivery

Dec 24

Midlands WA

RCP-R1-217

RCP-R1-217-I

Milling

Site acquired. Build schedule being finalised. Tower ready for delivery.

Dec 24

Midlands WA

RCP-R1-217

RCP-R1-217-J

Pithara

Site acquired but subject to negotiations with Main Roads WA. Build schedule being finalised.

Dec 24

Midlands WA

RCP-R1-217

RCP-R1-217-K

Kallanie

Site acquired. Build schedule being finalised.

Dec 24

Midlands WA

RCP-R1-217

RCP-R1-217-L

Wubin

Site acquired. Build schedule being finalised.

Dec 24

Midlands WA

RCP-R1-217

RCP-R1-217-M

Hospital Road

Site acquired. Build schedule being finalised.

Dec 24

Details about Mobile Deployment Code
Field Solutions Group, as a Carrier under the Telecommunications Act 1997, is required to comply with the Mobile Phone Base Station Deployment Industry Code C564:2020 when selecting a site and designing and operating Mobile Phone Radiocommunication infrastructure.

The Mobile Phone Base Station Deployment Industry Code is designed to:

  • allow the community and councils to have greater participation in decisions made by Carriers when deploying mobile phone base stations; and
  • provide greater transparency to local community and councils when a Carrier is planning, selecting sites for, installing and operating Mobile Phone Radiocommunications Infrastructure.

For further information on the Mobile Phone Base Station Deployment Industry Code, please click on the following link:

Communications Alliance – C564:2020 Mobile Phone Base Station Deployment (commsalliance.com.au)

As part of complying with the Mobile Phone Base Station Deployment Code, Field Solutions Group is also required to provide detailed information about any proposed Mobile Phone Radiocommunications Infrastructure via the Radiofrequency National Site Archive (RFNSA) website. Please follow the link below and enter the RFNSA Site ID number provided in the site lists above/below for detailed information.

https://www.rfnsa.com.au

 